Index  ›  science  ›  BBC
science · BBC ↗

Humber estuary flood defence scheme progressing well

BBC Reviewed Jun 30, 2026 ✓ Reviewed by citations.press editors
Citation-ready fact
The Environment Agency says the flood defence scheme costs £2.7 million.
2.7 GBP million · scheme cost
Environment Agency
View source ↗
Citation-ready fact
The Environment Agency reports that steel piles have been placed along a 900‑metre section of Halton Marshes.
900 metre · section length
Environment Agency
View source ↗
Citation-ready fact
The Environment Agency’s flood risk management plan for the estuary covers the next 25 years.
25 years · plan horizon
Environment Agency
View source ↗
Citation-ready fact
The Environment Agency expects the scheme to be completed in October.
Environment Agency
View source ↗

A £2.7m scheme to help protect land and businesses on the Humber estuary from flooding is progressing well, the Environment Agency has said.

Steel piles have been placed along a 900-metre section of Halton Marshes as part of the project, which started in September last year.

The Agency said this was now complete and rocks were being used to shore up the defences.

The scheme is expected to finish as planned in October.

The work is part of the Humber Estuary Flood Risk Management Strategy, which outlines the Environment Agency's flood risk management plan for the estuary for the next 25 years.