Thanet offshore wind farm nearing completion

BBC Published Jun 16, 2010 Reviewed Jul 2, 2026 ✓ Reviewed by citations.press editors
Citation-ready fact
Thanet Wind Farm supplied power to the National Grid for the first time on 16 May.
1 times · power supply to National Grid
View source ↗
Citation-ready fact
Thanet Wind Farm has more than 90 of the planned 100 wind turbines installed.
more than 90 turbines · installed wind turbines100 turbines · planned wind turbines
View source ↗
Citation-ready fact
Vattenfall owns the 30-turbine Kentish Flats wind farm.
30 turbines · wind turbines at Kentish Flats
View source ↗
Citation-ready fact
Project manager Ole Nielsen stated offshore wind turbines produce 50% more energy than onshore turbines.
50 percent · production increase
View source ↗
Citation-ready fact
Thanet Wind Farm is expected to generate enough electricity for 240,000 homes.
240000 homes · electricity generation
View source ↗
Citation-ready fact
Thanet Wind Farm is expected to be fully operational in the autumn.
1 seasons · full operational status
View source ↗
Citation-ready fact
The London Array project will install up to 341 turbines over a four-year period.
at least 341 turbines · turbines to be installed4 years · installation period
View source ↗
Citation-ready fact
Ole Nielsen, who has worked on 10 projects, said offshore wind farms could have up to 1,000 turbines in the future.
at least 1000 turbines · planned turbines in future offshore wind farms
View source ↗

A Swedish energy giant is gearing up to launch the world's biggest wind farm off the Kent coast.

Vattenfall is putting the last few turbines into place, but the project has been delayed by weeks because of high winds and rough seas.

The wind farm is expected to generate enough electricity for 240,000 homes.

With more than 90 of the planned 100 wind turbines installed, Thanet Wind Farm supplied power to the National Grid for the first time on 16 May.

The project, built by Swedish energy giant Vattenfall, is expected to be fully operational in the autumn.

"This is the future," said project manager Ole Nielsen.

"This is sustainable energy, and I don't think there is any way round it.

"Offshore windmills are much to be preferred to onshore.

"We have 50% more production on these turbines out here and it is not disturbing anyone onshore."

The construction vessel Resolution is currently working on the final few of the 380ft (115m) tall turbines being built seven miles (12km) off Foreness Point in Thanet.

Construction started a year ago at the £780m wind farm, which can be seen from the coast on a clear day.

The company also owns the 30-turbine Kentish Flats wind farm, off Herne Bay, which was one of the UK's first such projects when it opened five years ago.

Mr Nielsen, who has worked on 10 projects, added that wind farms were getting bigger and bigger.

The London Array project in the Thames Estuary, for which energy firm E.ON is a major backer, will enter its offshore construction phase next year.

In all, up to 341 turbines will be installed over a four-year period.

Mr Nielsen said that in the future, offshore wind farms could have up to 1,000 turbines.

This article was originally published by BBC ↗. citations.press indexes the source-backed facts above and links to the original. Something wrong? Corrections policy · Report an error