“The county council is resurfacing a 1.7km section of the A54 on the Buxton side in two phases, external, the first of which started in July and is due to run until October.”
“The work, which involves lowering the weir to reduce the volume of water and remodelling the downstream slope of the dam to increase its stability, is due to be completed by the end of November.”
“Derbyshire County Council said a project to stabilise the dam at Osborne's Pond means Shipley Lane bridleway will be closed at the point it crosses the dam - close to the entrance from Roper Avenue -…”